Capital project moves forward as board OKs bids for maintenance building
While not much physical progress has been seen over the last few weeks on Liberty Central School District’s capital projects, there has been movement behind the scenes.
The initial capital project was approved by voters in January 2024, with additional HVAC upgrades approved in the 2025 project to address state-mandated temperature limits in classroom spaces.
Phase 1
The largest was the approval of contracts for the construction of the maintenance building on Winthrop Avenue near the softball and soccer fields.
At a meeting last month, the Board of Education approved contracts as follows:
- General Construction: Standback General Contractors LLC
- Mechanical Construction: C.R.Wolfe Heating Corp.
- Plumbing Construction to S&O Construction Services Inc,
- Electrical Construction to Hewitt Young Electrical LLC,
- Site Construction to NGS Construction
- Construction is expected to begin this spring.
In other aspects of Phase 1:
The turf field, lights, goal posts and goals have been installed on the athletic fields, as has the foundations for the bleachers and pressbox. The bleacher and pressbox installation is expected to take place early spring, with the installation of the track and track and field components this spring. The field is expected to be completed in time for graduation.
The bid for door replacement in the middle and high schools was also finalized last month, with the replacements expected to be completed in the spring.
Phase 2
The second phase of the capital project, which includes work at the high school and middle school, has been submitted to the state Education Department for approval, with work expected to begin in the early summer
The work at the high school includes renovations in the 300 wing and cafeteria, creation of the Innovation Lab, a generator replacement, stair removal, and upgrades to the HVAC controls, carbon monoxide alarm system and code-mandated items.
The work at the middle school includes site drainage improvements, replacement of the electrical main distribution panel and some internal doors, upgrades to the HVAC controls and carbon monoxide alarm system and a new emergency generator.
Phase 3
The final phase of the project includes work at the elementary school and the district office. The project is in the design phase with work expected to take place in 2026 and 2027.
The work at the district office includes carbon monoxide alarm system upgrades and a new emergency generator.
The work at the elementary school includes roofing repairs and upgrades, asbestos flooring abatement and replacement, wood flooring replacement, new complaint railing on the interior bleachers in the gym, and carbon monoxide alarm system and gym ventilation upgrades. HVAC work includes unit ventilator upgrades in the classrooms, boiler conversion to accommodate the additional air conditioning and HVAC control upgrades.
LAN Associates, the project architect, has completed all major architectural and mechanical site survey work, with additional visits to the school needed as the design is developed and finalized. The HVAC load calculations were finalized earlier this year, and the preparation of demolition drawing is ongoing. The options for providing ventilation air in the gymnasium are being reviewed and coordinated. LAN has also been in communication with Day Automation, which provides energy services to the district, in regard to the boiler replacement in the original building or expansion of the existing boiler plant.
“We thank LAN and our construction manager Schoolhouse Construction Services for their work on these projects,” LCSD Superintendent Dr. Patrick Sullivan said. “These projects will provide our students with the best environment to help our students contribute and thrive in a diverse community by pursuing their potential.”